There is a minor conflict between several members on a project team; the issue has no significant
impact on the project.Which of the following would be the BEST conflict resolution technique for the project manager to employ?

A. Avoiding
B. Forcing
C. Compromising
D. Confronting

Answer: A

Question No:2

A customer has requested an increase in the scope of a current project, but the project schedule
remains the same.Which of the following is MOST likely impacted? (Select TWO).

A. Project quality
B. Project cost
C. Project baseline
D. Project milestones
E. Deployment plan

Answer: A,B