A project team member has identified a required change to one of their assigned tasks. The change would alter the order in which other tasks must be completed.
Which of the following should be done NEXT?


A. Implement the change
B. Update the change registry
C. Document the change
D. Perform an impact analysis

Answer: D


Which of the following should be used when determining the details of a project component or scope entry?


A. WBS Dictionary
B. Project Management Plan
C. Work Breakdown Structure
D. Project Charter

Answer: A

Sunday 5 August 2018

CompTIA PK0-003 Question Answer

A new software solution is being deployed. The customer realizes that an important piece of the software must be purchased in order for the project to be successful. Which of the following is TRUE about this scenario?

A. The new piece of software will most likely expand the scope of the project therefore a new scope statement must be written.
B. The current project must be completed and a new project can be started to implement the additional software.
C. Quality management metrics are affected therefore the project manager should review the quality of the project.
D. Project schedule may be affected and the project manager must follow the change control process.

Answer: D


While performing a scheduled walkthrough at a construction site, the customer points out a discrepancy. Which of the following is the FIRST step that should be taken before submitting a change control form?

A. Consult the project sponsor
B. Identify the change
C. Perform a feasibility study
D. Perform impact analysis

Answer: B

Tuesday 27 February 2018

CompTIA PK0-003 Question Answer

One of the MAIN purposes of a kick-off meeting is to:

A. Assign and review roles and responsibilities to the project team.
B. Allow the project sponsor to introduce the project manager to the team.
C. Review the project definition document and make the appropriate changes.
D. Ensure project team members communicate amongst each others.

Answer: A


After the ground breaking at a new construction site, the pile driving operation comes to a full stop due to the nature of the terrain. Which of the following is MOST likely to occur?

A. The project communication plan must be updated and a stakeholder meeting must be scheduled.
B. The project manager must manage the new issue as the project schedule could be delayed.
C. The project manager must implement conflict resolution and review the resource requirement.
D. The project scope statement must be reviewed and the project manager must prepare a performance report.

Answer: B

Wednesday 27 December 2017

Preparing for a career


Harford Community College has partnered with FreeState ChalleNGe Academy for more than 20 years to help cadets earn high school diplomas and transition to postsecondary education and employment. Together, they have established the course for young people to succeed and develop their full potential.

HCC provides supplemental GED preparation instruction, professional development, curriculum and instructional resources for FreeState instructors; work observation experiences for cadets; a $ 5,000 scholarship for a cadet who plans to pursue postsecondary education at the university; and support to help the Harford County cadets with the transition to HCC.

At the recent community meeting of senior leaders of Aberdeen Proving Ground at Rockfield Manor in Bel Air, Brandy Naughton, dean of Community Education, and Pamela Karwowski, director of government training, contractors and IT, talked about the partnership between FreeState ChalleNGe Academy and Harford Community College. .

Naughton talked about HCC's multi-year relationship with APG and the FreeState ChalleNGe Academy of Maryland, while Karwowski addressed the training partnership in occupational education and driving with FreeState that took place this fall. APG community meetings help strengthen the relationship between APG leadership and the local community by showing partnerships and addressing issues of mutual interest.

Maryland is one of the 10 original states to start a ChalleNGe Program in 1993 under Public Law 102-484. The academy is located in APG and is run under a cooperative agreement between the Maryland National Guard and the National Guard. The academy is a free program that offers adolescents at risk from 16 to 18 years of age the opportunity to change their future for the better by providing the skills, education and self-discipline necessary to become responsible and productive citizens.

The "hard love" approach used in the program has helped graduate over 4,000 cadets since the program began in 1993. The initial program consists of a 22-week residential phase. During this phase, cadets learn self-discipline, leadership and responsibility. Participants live and work in a controlled military environment, fostering teamwork and personal growth.

A post-residential phase of 12 months focuses on helping enroll graduates in continuing education, technical school programs or entry-level jobs. During the post-residency phase, students receive assistance from at least one trained mentor from the community for further development.

Work observation components include work experience, college orientation, meeting with admissions, application completion and placement testing, and participation in student activities. The goal is for students to learn what it is like to be an HCC student and employee.

Earlier this year, the cadets came to HCC to participate in an interactive presentation of the career panel with other GED students. The cadets learned how to present themselves professionally and how to avoid the pitfalls that can be associated with the social networks of community leaders in human resources, marketing and professional services.

This fall, the FreeState ChalleNGe Academy hired HCC to provide vocational training and driver education for its Fall 2017 cohort of more than 100 cadets. The program provided the cadets with academic, work and life skills training and emphasized positive values ​​in a structured environment. The training began in October of this year and will be completed this month.

HCC supported this mission by providing training to cadets in A + Certification Preparation, 90-Hour Certificate for Child Care Professionals, Introduction to Arc Welding, OSHA 10-Hour Certification, Applied Culinary Arts Certification, Classroom Instruction Driver Education and Driver Education Driver behind the wheel instruction at various locations in the area, including Harford Community College, the Edgewood Public Library, Harford Technical High School and FreeState ChalleNGe Academy at APG-South.

Cadets in the Applied Culinary Arts program learned practical cooking skills and equipment while creating delicious foods such as handmade spring rolls and chocolate cake from scratch. The skills learned could translate into a variety of careers related to food science.

Some cadets were students in A + Certification Preparation, a practical program designed to prepare them to take and pass the two A + exams needed to become CompTIA A + Certified. Once the cadets complete the courses, they will have the knowledge and confidence to pass the exams and the necessary skills to be a great PC technology. Your new skills will help you get your first job in PC technology and / or start your education in cybersecurity.

The arc welding students were introduced to arc welding machines and accessories, and learned different types of welds, joint designs and safety practices, all the skills that could lead to employment in this industry.

The partnership between HCC and FreeState ChalleNGe Academy was created to provide training that leads to jobs in sustainable careers / occupations for these youth. As both organizations reside in Harford County, this partnership can succeed, both logistically and administratively.

 

https://ics.instructure.com/eportfolios/594/Institute_For_Knowledge/Salesforce_Certified_Administrator_ADM201
https://dcds.instructure.com/eportfolios/231/Institute_For_Knowledge/Microsoft_MCSA_SQL_2016_70764_Test
https://edu-24.info/eportfolios/5677/Learning_Tree/Get_here_best_solution_to_pass_the_QlikView_QSDA2019_in_2021_with_Qlik_Sense_Questions
https://isp.instructure.com/eportfolios/6439/Start_Smart/How_To_Find_Authentic_Solution_For_The_Preparation_Of_Palo_Alto_Networks_PCNSE_Exam_With_No_Fear
https://sdhc.instructure.com/eportfolios/2786/Learning_Tree/Juniper_Networks_Junos_Associate_JN0103_ExamJunos_Associate_Exam_2021_Questions



https://gopoco.us/How_To_Pass_The_PCNSE_Exam/NTky
https://www.wikilistia.com/list/get-perfect-jn0-103-exam-questions-from-braindumps4it-jn0-103-junos-associate/
https://www.thewyco.com/news/-salesforce-administration-essentials-for-new-admins-adm-201-braindumps-questions-16-11-2020
https://trumpbookusa.com/blogs/194731/Microsoft-70-764-Exam-Dumps-70-764-Administering-an-SQL
https://loopia.network/read-blog/3477


https://global-gathering.com/opinions/3191
https://www.gammahoteles.com/web/braindumps4it/home/-/blogs/1382182
http://www.cs.infn.it/web/braindumps4it/home/-/blogs/get-top-quality-qlik-sense-qsda2019-exam-dumps-with-latest-qlikview-qsda2019-questions-2021-?_33_redirect=http%3A%2F%2Fwww.cs.infn.it%2Fweb%2Fbraindumps4it%2Fhome%3Fp_p_id%3D33%26p_p_lifecycle%3D0%26p_p_state%3Dnormal%26p_p_mode%3Dview%26p_p_col_id%3Dcolumn-2%26p_p_col_count%3D1
https://innovation.cccb.org/web/braindumps4it/home/-/blogs/which-are-the-main-benefits-of-palo-alto-networks-pcnse-exam-in-2021-?_33_redirect=https%3A%2F%2Finnovation.cccb.org%2Fweb%2Fbraindumps4it%2Fhome%3Fp_p_id%3D33%26p_p_lifecycle%3D0%26p_p_state%3Dnormal%26p_p_mode%3Dview%26p_p_col_id%3Dcolumn-2%26p_p_col_count%3D1
http://idiomas.uabc.mx/web/braindumps4it/home/-/blogs/82301
 

Wednesday 13 September 2017

CompTIA PK0-003 Question Answer

Which of the following is the MAIN difference between bottom up and top down cost estimation?

A. Bottom up leads to a more accurate cost estimate than top down because it is performed by subject matter experts
B. Top down leads to a more accurate cost estimate because it is performed by upper management with direct access to budget information
C. Bottom up leads to a less accurate cost estimate because it is breaks down the task into smaller subtasks where some tasks may not have a cost
D. Both top down and bottom up are equally accurate estimation of a project's total cost because they both refer to resources assigned by the project sponsor

Answer: A


Which of the following purchasing processes should a project team use to ensure that the work will be done per company specifications, while selecting the overall cheapest provider?


A. RFI
B. RFP
C. RFC
D. RFQ

Answer: B

Thursday 4 May 2017

CompTIA PK0-003 Question Answer

A project manager is entering the list of a project's activities with their estimated begin and end time to visualize which activities overlap and when the project is scheduled to end. Which of the following is the project manager building?

A. Gantt chart
B. Work Breakdown Structure
C. Critical Path
D. PERT chart

Answer: A


The project manager is sequencing a set of activities. They discover that some of the activities may or may not occur based on the outcome of other activities. Which of the following is BEST suited in this situation to show the activities' logical relationship?


A. Gantt
B. ADM
C. CCB
D. CCM

Answer: B

Wednesday 9 September 2015

Pass4sure PK0-003 QUestion Answer

Which of the following MUST be clearly defined in a project charter? 

 

A. Quality
B. Scope
C. Action items
D. WBS

Answer: B

 

 

Which of the following is used to provide a functional description of the efforts which are required in order to accomplish a task? 

A. Gantt chart
B. PERT
C. GERT
D. WBS dictionary

Answer: D 

 