CompTIA PK0-003 Questions Answers

A project team member has identified a required change to one of their assigned tasks. The change would alter the order in which other tasks must be completed.
Which of the following should be done NEXT?


A. Implement the change
B. Update the change registry
C. Document the change
D. Perform an impact analysis

Answer: D


Which of the following should be used when determining the details of a project component or scope entry?


A. WBS Dictionary
B. Project Management Plan
C. Work Breakdown Structure
D. Project Charter

Answer: A