A project manager is entering the list of a project's activities with their estimated begin and end time to visualize which activities overlap and when the project is scheduled to end. Which of the following is the project manager building?

A. Gantt chart
B. Work Breakdown Structure
C. Critical Path
D. PERT chart

Answer: A


The project manager is sequencing a set of activities. They discover that some of the activities may or may not occur based on the outcome of other activities. Which of the following is BEST suited in this situation to show the activities' logical relationship?


A. Gantt
B. ADM
C. CCB
D. CCM

Answer: B